Sunday, January 27, 2013

Seven Tips To Maximize The Performance And Effectiveness Of Your PMO


Here are seven tips for maximizing the performance and effectiveness of your PMO:

1.  Ensure all projects have a Project Dashboard, displaying a comprehensive and standard set of project metrics
-  This standard set should include at least Project Schedule Performance, Project Cost Performance, Client Satisfaction, Team Satisfaction and  Project Resourcing metrics.
-  These metrics should all be in the form of indices, to allow a better and more meaningful comparison between all projects.
-  Every Project Dashboard should be made visible to all (excluding any financial or other confidential information).

2.  Aggregate the above key Project Data and display as a PMO Dashboard
-  Each of the project metrics should be averaged across all projects and the results displayed on a monthly trending chart, to show improvement (or not) in the performance of projects in each area measured.
-  The PMO Dashboard should also be made visible to all.

3.  Ensure your projects are aligned with the strategic goals and objectives of your organization (and that of your clients, if in different organizations)

4.  Foster an organization culture that will facilitate the success of your PMO
-  Foster a supportive, collaborative and co-operative culture with project and PMO executive and client management, project managers and all other key stakeholders, to facilitate the successful achievement of project and PMO goals and objectives.

5.  Focus on project results, not project management methodologies and processes
-  With the project and PMO dashboards in place, and a focus on getting the best performance and results for each project, better decisions are going to be made regarding the appropriate project management methodologies, processes, tools and templates needed to achieve these results.  

6.  Facilitate the successful initiation and support of all projects.
-  Establish a core group of experienced project managers, made available as needed, to ensure the successful initiation of all projects.  (This group can be staffed within the PMO, or borrowed from project teams on a scheduled and prearranged basis, as appropriate).
-  Provide ongoing oversight and support through this group, as needed to maintain project success.

7.  Foster continuous improvement in project performance and results
-  Make the training and development of project managers and their project teams a committed and measurable objective.
-  Ensure skilled resources are provided as and when needed for each project.
-  Synthesize, disseminate and act on Lessons Learned from all projects.

Are there any other tips you would like to add?

If you would like to learn how these and many other useful tips and techniques can be applied to benefit your PMO, contact us to arrange a four hour PMO Workshop that can be held on-site or via our web conferencing facilities. 

Sunday, July 22, 2012

Never Underestimate The Power Of A Project Dashboard




In 2003, the Virginia Department of Transportation (VDOT) introduced a web based Dashboard for their construction projects. 

This Dashboard became a powerful tool for VDOT Executive and Project Managers, showing instantly whether projects were on track, falling behind schedule or going over budget.



The Dashboard was soon made public, and citizens were invited to view the Dashboard online and share their comments.  The performance improvement achieved by all VDOT projects was dramatic.

Prior to the introduction of the Dashboard in 2003, less than 20% of all projects were on time. By 2005, this number had improved to 75% and currently, as you can see from the VDOT Dashboard above, 97% of all projects are on time - an outstanding improvement in a very complex and challenging construction project environment.  Similar improvements were achieved in the other areas measured by the Dashboard.

As you can see from the VDOT example, a Project Dashboard can indeed be a very powerful and effective project management tool.

To be effective, a Project Dashboard should follow these following eight principles:
  • Use a standard dashboard format across all projects - in this way, the performance for all projects can be fairly and effectively compared.
    Information displayed should include the Project Schedule, Project Budget, Client Satisfaction Index, Project Resourcing Index and Project Health Check Index metrics.  A summary of the key Project Milestones and Project Risks and Issues should also be displayed.  (See the sample AlphaPM Project Dashboard tool layout above)
  • Ensure the dashboard is easy to understand - it should be easy to determine the performance of the project by using Green/Yellow/Red icons to show the performance of the project through the various key metrics.  Avoid clutter, and keep metrics and information displayed to the minimum useful set.
  • Ensure the dashboard is easy to complete - the metrics on the dashboard should be easy to measure, collect and present
  • Provide background information through a "drill down" capability - detailed information (such as the project schedule, risk register, project health check detailed results, project repository, status reports and change requests) should be linked to the dashboard, so that they can be referenced as needed. 
  • Make sure all information is timely and updated at least weekly - if it is not, it will be ignored.
  • Provide maximum visibility of the dashboard to all stakeholders - this will motivate the project team to keep on track and also ensure that the Executive and all other project stakeholders know if a project is in trouble, so that they can promptly assist in addressing problem areas. 
  • Show the project's business goals and objectives -  add a short section with a few bullets on the business goals and objectives for the project.  This helps to reinforce the importance and value of the project and keep all stakeholders focused on meeting the project's business goals. 
  • The organization must have a supportive culture
    Now here's the most challenging part of ensuring that Project Dashboards are indeed successful.  The organization culture (starting with your Executive and Client Management) must be proactive and constructive in their support of projects who show red or yellow metrics on the dashboard.

    For example, say your Executive meets you in the hallway and has noticed that your project has some red metrics on your Project Dashboard.
    Bad:  Executive says to you "Why is your project in such a mess and when are you going to have it fixed?"
    Good:  Executive says to you "I see you are having some challenges on your project.  Is there anything I or my management team can do to help you get back on track?"

    Without a supportive and collaborative executive and organization culture, project managers will resent having visible dashboards, and start to fudge metrics and cover up issues and problems, thus making them even more difficult to eventually solve.

Let us know your experiences and best practices with Project Dashboards.


Webinar:  APM13 Project Dashboards
If you are interested in learning more about Project Dashboards, and would like the AlphaPM Excel based Project Dashboard tool, sign up for our one hour APM13 "Project Dashboards" webinar at www.alphapm.com/webinars


For further information on Client Satisfaction metrics and Project Dashboards, please see these previous posts:
Client Satisfaction Surveys the Easy Way
Six Best Practices For Managing Multiple Projects

Sunday, July 1, 2012

Client Satisfaction Surveys The Easy Way

Client Satisfaction is one of the key measures of success for any project.  Yet I find, too often, that project managers do not formally check with their clients on whether they are satisfied with the progress of their project.

In a couple of organizations where I have worked, I suggested that we carry out Client Satisfaction Surveys and the idea was always well supported.  In one organization, a highly detailed and overly complex questionnaire was developed, with poor results, and in the other organization the survey was still being scientifically designed when I left over six months later.

I think Client Satisfaction Surveys are absolutely necessary for all projects, but I also think they should be very simple, for the benefit of both the client and the project manager.

Here is my recommendation for a simple survey that can be completed quickly and easily with your client sponsor, yet will provide you with a valuable gold mine of information.
 
Let me walk through the various sections of the survey:

Please provide us with your overall satisfaction with the project (check one)

Notice I have kept the satisfaction levels to an absolute minimum.  Your client is either completely satisfied, dissatisfied or somewhere in between.  Don't try and grade various levels of "in between".  It really does not matter - some things need to be fixed and that's all you need to know.   By keeping it simple, you are more likely to keep up the practice of doing the survey, you make it easier for your client sponsor to pick the right level, and you can compare satisfaction levels across projects in a more consistent way.

The levels should be associated with a dashboard indicator icon (green, red, yellow) and the appropriate icon should be shown on your Project Dashboard, with a drill down capability to the details provided in this survey.
Your PMO should aggregate all individual project survey results (using say, 1 for each red, 3 for each yellow and 5 for each green), and then show the average rating for all projects.  By tracking this average on a monthly basis, the PMO can see if they are helping all projects to improve client satisfaction.


What aspects of the project are working well?

It is always a good idea to start on a positive note.  This will help to balance the survey and give positive reinforcement to the good processes being used and good work being done by the project manager and project team.


What aspects of the project could be improved?


The client sponsor should summarize here any areas they feel need to be improved, whether processes, people or results.  Bullet points should suffice.  If the project manager needs more detail, they should discuss this in a separate session.  Again, the purpose here is to keep the process simple.


Are there any other comments you would like to add?

This space can be used by the client to add anything they wish about the project, project manager or project team.  


Some Survey "DOs" and "DON'Ts"

-  DO the survey privately and in person with your Client Sponsor (for example, after a regular status meeting or during a lunch meeting).
-  DO the survey regularly (monthly is good).
-  DO make sure that you address all items raised as needing improvement before the next survey.
-  DO make the results of the survey visible on your project dashboard to all (your project team, your management, client management).  Visibility always help to make sure problems are addressed promptly, one way or another.

-  DON'T try and respond during the survey review meeting to any problem areas being raised (unless to just request any needed background information on the problem).  Any immediate defense of noted problem areas will only raise the ire of your client and serve no useful purpose.  Better to reflect on all the items raised and come back in a separate session to show your client how you and your project team  have addressed or will address all problem areas raised in the survey.

Client Satisfaction Surveys are an extremely easy and powerful tool for building your project's success.  If you are not doing them regularly, I hope you will try one out soon.

Let us know about any Client Satisfaction Survey practices that are working well for you.

Sunday, June 17, 2012

Six Best Practices For Managing Multiple Projects


In this struggling economy, project managers are often required to manage many projects. It is usually a challenge to manage just one project, so it is inevitable that managing multiple projects will pose even more challenges.

How many projects can a project manager manage?
Now there are so many factors that affect this determination (e.g. project size, type and complexity, resources and skills available, number of clients, location and duration of projects etc.), that it is impossible to quote any useful number.  I think it will be fair to say, however, that you can manage more than you might have believed possible, if you apply the following six best practices.


Management Support
1.  Ensure the support and trust of your management and client management.
Perhaps the most valuable of all best practices is to ensure you have the support and trust of your management, client sponsor and client management.  Their proactive support is essential for the timely resolution of many activities (e.g. scope definition, project budget, resourcing, issue resolution, project prioritization etc.).  Be open about the need for their support, and take advantage of every opportunity to gain it (for example, through your project kickoff meetings, risk reviews, regular status meetings and steering committee meetings).

Resourcing
2.  Ensure you have the appropriate level of skills and resources.
This is easier said than done, but it is essential if you are to be successful in managing your many projects. Identify up front the specific skills and resources that you need for your projects, and persevere until you get them. Look for people who are team players, adaptable and willing to work in many different capacities.

Resources should ideally be dedicated to your projects and co-located.  If you cannot get fully dedicated resources, at least make sure they are co-located on specific days each week. so that you can count on their availability and support.

Performance Reporting
3.  Establish a Project Dashboard for all your projects.


Use a simple dashboard like the one shown here, to  give clear visibility to the status of your projects.

The projects can be sorted by client, so that each client sees the status for only their projects.


A Dashboard is an extremely powerful tool for soliciting the support of your project stakeholders, so ensure that the "Comments" shown for each project reflects the actions you are taking and/or the support you need to address the "yellow" and "red" areas that need resolution.  



Time Management
4.  Ensure you and your team members practice good time management.
Establish with your project team the most effective ways you can maximize your team productivity and build these into your Team Operating Agreement and practice them.
For example:
-  Keep meetings short and focused.  Take individual issues offline rather than trying to solve them at team meetings.
-  Ask your team members to let you know early if they are going to be late on an activity, so that you can take any corrective action necessary to keep the activity from being delayed.


Delegation
5.  Delegate to the max.
When managing many projects, there is quite often a tendency for project managers to take on more work themselves, since they feel their team members are already overloaded.  Wrong approach! They should delegate all activities, so that they can free themselves to work with their team leads to address issues and provide support, as opposed to being locked away trying to do activities that can and should have been delegated.
Establish a project lead for each project, or set of projects, so that you can act as the overall program manager to ensure all projects are successfully completed.


Methodology
6.  Apply a methodology that is scalable and adaptable to your project needs.
The methodology that your organization has established may not work well with your set of projects.  It is important that you adapt and scale the key elements of the organization's methodology to fit your many projects.
For example:
-  Use the simple Project Dashboard shown above for all your projects, rather than a one page Dashboard for each project.  This Dashboard can act as your Status Report for all your projects.
-  Do a combined Risk Assessment for all your projects, rather than one for each project.

Are there any other best practices for managing multiple projects that you can recommend?


Webinar:  APM13 Project Dashboards

If you are interested in learning more about Project Dashboards, and would like an Excel based Project Dashboard tool, sign up for our one hour APM13 "Project Dashboards" webinar at www.alphapm.com/webinars